What do you do when your garage just isn’t enough space anymore?

For this Scottsdale, AZ home, the solution was a 946 square foot attached garage addition paired with interior updates to support how the space would actually be used. Built with high ceilings and a wide-open layout, the addition gives the homeowners room for storage, projects, and everyday use without feeling cramped or disconnected from the home. The result is a clean, functional space that works just as hard as the rest of the house.

Project Overview

  • Project Type: Attached RV garage with bathroom and other interior remodeling

  • Size: 946.8 sq. ft

  • Location: Scottsdale, AZ

  • Use: Private RV storage with integrated bathroom

  • Year Built: 2021
  • Connection:Attached addition integrated into the existing home, with structural tie-in, shared utilities, and seamless exterior and roofline transition

Cost Breakdown

$0
Approximate Total Project Cost
$0
Approximate Cost Per Square Feet

What This Cost Included

This project cost included the full scope of design coordination, engineering, and permitting required for a garage addition and interior reconfiguration in Scottsdale, Arizona .

Construction costs covered all major phases of the build, including demolition of existing walls, new concrete foundation work, rough carpentry, roof framing, roofing, exterior stucco, insulation, drywall, and finish carpentry to integrate the new structure with the existing home.

Mechanical, plumbing, and electrical systems were installed through both rough-in and trim-out phases, including a mini split system to provide efficient heating and cooling for the new space, along with utility connections tying into the existing home.

Interior work included modifications to existing living areas, conversion of garage space, and finishes such as flooring, trim, and painting to create a cohesive and functional layout throughout.

Project management, general conditions, overhead, and contractor profit were included to coordinate the work, manage scheduling, and deliver the project from start to finish.

Description Final Cost Price per sq. ft.
Demolition $6,120.00 $6.46
Termite
Treatment
$493.00 $0.52
Concrete $12,990.00 $13.72
Rough Carpentry $17,700.00 $18.69
Roofing $4,697.00 $4.96
Mechanical –
Rough in
$2,189.00 $2.31
Plumbing –
Rough in
$6,302.91 $6.66
Electrical –
Rough in
$7,980.00 $8.43
Windows, Glass
& Glazing
$2,601.17 $2.75
Insulation $3,833.27 $4.05
Stucco / Siding $7,794.00 $8.23
Drywall $4,658.00 $4.92
Tub/Shower
surround
$6,095.00 $6.44
Painting $3,838.00 $4.05
Finish Carpentry
& Cabinets
$989.00 $1.04
Flooring $3,270.00 $3.45
Baseboards $600.00 $0.63
Garage Door $4,039.00 $4.27
Subtotal $96,189.35  
Overhead Profit (18%) $17,314.08  
Grand Total $113,503.43 946.8 sq. ft
Cost per sq. ft   $119.88

Costs shown reflect actual construction costs for this project at the time it was built. Pricing varies based on scope, finishes, site conditions, and market factors.