Pricing Breakdown
*The below costs are actual costs of the above project.
*Pricing is subject to change and all jobs are unique.
Note this addition included the garage and a full sized bathroom.
Description | Final Cost | Price per sq. ft |
Termite | $590.00 | $0.61 |
Concrete | $20,495.00 | $21.30 |
Rough Carpentry | $25,490.88 | $26.50 |
Roofing | $10,093.06 | $10.49 |
Mechanical Rough In | $2,480.00 | $2.58 |
Plumbing Rough In | $11,066.82 | $11.50 |
Electrical Rough In | $5,499.30 | $5.72 |
Windows, Glass and glazing | $3,424.12 | $3.56 |
Insulation | $2,530.06 | $2.63 |
Stucco/Siding | $6,550.00 | $6.81 |
Drywall | $6,800.00 | $7.07 |
Tub/Shower Surround | $7,493.42 | $7.79 |
Painting | $4,500.00 | $4.68 |
Finish Carpentry & Cabinets | $2,909.00 | $3.02 |
Countertops | $180.00 | $0.19 |
Flooring | $508.37 | $0.53 |
Baseboards | $167.98 | $0.17 |
Garage Doors | $4,275.00 | $4.44 |
Plumbing – Trim out | $2,762.50 | $2.87 |
Masonry Non-Structural/ Fences | $4,732.50 | $4.92 |
Temporary Toilet | $2,013.82 | $2.09 |
Dumpsters | $2,091.49 | $2.17 |
Equipment Rentals | $4,017.04 | $4.18 |
Misc. | $2,792.31 | $2.90 |
Engineering & Professional Services | $4,650.00 | $4.83 |
Permit Costs | $1,827.13 | $1.90 |
Supervision/Labor | $13,358.15 | $13.89 |
Subtotal | $153,297.95 | |
Overhead Profit (20%) | $30,659.59 | |
Grand Total | $183,957.54 | 962 sq. ft |
Cost Per Sq. Ft | $191.22 |