*The below costs are actual costs of the above project.
*Pricing is subject to change and all jobs are unique. 

Description Final Cost Price per sq. ft.
Demolition $6,120.00 $6.46
Termite
Treatment
$493.00 $0.52
Concrete $12,990.00 $13.72
Rough Carpentry $17,700.00 $18.69
Roofing $4,697.00 $4.96
Mechanical –
Rough in
$2,189.00 $2.31
Plumbing –
Rough in
$6,302.91 $6.66
Electrical –
Rough in
$7,980.00 $8.43
Windows, Glass
& Glazing
$2,601.17 $2.75
Insulation $3,833.27 $4.05
Stucco / Siding $7,794.00 $8.23
Drywall $4,658.00 $4.92
Tub/Shower
surround
$6,095.00 $6.44
Painting $3,838.00 $4.05
Finish Carpentry
& Cabinets
$989.00 $1.04
Flooring $3,270.00 $3.45
Baseboards $600.00 $0.63
Garage Door $4,039.00 $4.27
Subtotal $96,189.35  
Overhead Profit (18%) $17,314.08  
Grand Total $113,503.43 946.8 sq. ft
Cost per sq. ft   $119.88